Mitigation Measures against Coastal Erosion- Val-Comeau Provincial Park
Tracadie-Sheila, New Brunswick
Federal contribution
$600,000
Federal share50%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 22, 2026
20252026
Built
Approved 2 years before the announcement.
- Program
- Disaster Mitigation and Adaptation Fund
- Ultimate recipient
- New Brunswick Department of Tourism, Heritage and Culture
- Construction start
- Dec 1, 2024(actual)
- Construction end
- May 2, 2025(actual)
Against the original forecast
- Construction start14 months lateforecast Sep 24, 2023
- Construction end20 months earlyforecast Dec 17, 2026
Also in Tracadie-Sheila
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 121281 in the federal list. How to read these figures.