Back to projects

RMT Cycle Route - Interconnection and Signage

Tracadie-Sheila, New Brunswick

underwayActive TransportationATF
Federal contribution
$1.9M
$1,885,148
Federal share60%

of $3.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 21, 2023
2023202420252026
BuiltForecast

Approved 7 months before the announcement.

Program
Active Transportation Fund
Construction start
Dec 23, 2022(actual)
Construction end
Mar 31, 2026(forecast)

Against the original forecast

  • Construction start5 months earlyforecast May 31, 2023

Also in Tracadie-Sheila

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64566 in the federal list. How to read these figures.