Control Building - Aqueduct and Supply Design

Tracadie-Sheila, New Brunswick

completeDrinking WaterCWWF
Federal contribution
$278,913
Federal share47%

of $599.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2017
20172018
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jul 3, 2017(actual)
Construction end
Apr 30, 2018(actual)

Against the original forecast

  • Construction end19 months earlyforecast Nov 30, 2019