Improvements to Tracadie Sector Lagoon
Tracadie-Sheila, New Brunswick
Federal contribution
$3.0M
$2,971,281
Federal share49%
of $6.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 20, 2017
2017201820192020
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Regional Municipality of Grand Tracadie-Sheila
- Construction start
- Apr 5, 2019(actual)
- Construction end
- Mar 12, 2020(actual)
Against the original forecast
- Construction end4 months lateforecast Oct 31, 2019