completeDrinking WaterMRIF
Federal contribution
$1.4M
$1,427,387
Federal share33%

of $4.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 27, 2007
2008200920102011
Built

Approved 2 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Tracadie-Sheila
Construction start
Apr 16, 2007(actual)
Construction end
Aug 31, 2011(actual)

Against the original forecast

  • Construction start7 weeks earlyforecast Jun 1, 2007
  • Construction end2.8 years lateforecast Oct 31, 2008

Also in Tracadie-Sheila

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14539 in the federal list. How to read these figures.