Van Gorda Creek Crossing

Faro, Yukon

completeWastewaterMRIF
Federal contribution
$29,497
Federal share33%

of $88.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 18, 2005
20062007
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Faro
Construction start
Jun 15, 2005(actual)
Construction end
Dec 21, 2006(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Jul 4, 2005
  • Construction end15 months lateforecast Sep 30, 2005

Also in Faro

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12851 in the federal list. How to read these figures.