Replacement of the Glen Allan Bridge
Federal contribution
$1.1M
$1,109,667
Federal share33%
of $3.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2006
2007
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- County of Wellington
- Construction start
- Apr 20, 2006(actual)
- Construction end
- Jul 13, 2007(actual)
Against the original forecast
- Construction start17 months lateforecast Nov 16, 2004
Also in Mapleton
- Drayton Sewage Pumping Station Upgrades$2.1M
- Moorefield Water System Renewal$2.0M
- Replacement of Denstedt Bridge$309.0K
- Retrofit of Washrooms & A/V equipment in PMD Arena$80.0K
- Install six new watermain valves and rehabilitate two watermain valves within the Drayton water distribution system to address system deficiencies and improve operational flexibility$38.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13804 in the federal list. How to read these figures.