Replacement of Denstedt Bridge
Federal contribution
$309,000
Federal share33%
of $927.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2006
20072008
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Mapleton
- Construction start
- Apr 20, 2006(actual)
- Construction end
- Aug 28, 2008(actual)
Against the original forecast
- Construction start12 months lateforecast Apr 21, 2005
- Construction end5 weeks earlyforecast Sep 30, 2008
Also in Mapleton
- Drayton Sewage Pumping Station Upgrades$2.1M
- Moorefield Water System Renewal$2.0M
- Replacement of the Glen Allan Bridge$1.1M
- Retrofit of Washrooms & A/V equipment in PMD Arena$80.0K
- Install six new watermain valves and rehabilitate two watermain valves within the Drayton water distribution system to address system deficiencies and improve operational flexibility$38.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13945 in the federal list. How to read these figures.