Back to projects

Install six new watermain valves and rehabilitate two watermain valves within the Drayton water distribution system to address system deficiencies and improve operational flexibility

Mapleton, Ontario

completeDrinking WaterCWWF
Federal contribution
$38,500
Federal share50%

of $77.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 19, 2017
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Mapleton
Construction start
Jun 1, 2017(actual)
Construction end
Dec 15, 2017(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 1, 2017
  • Construction end2 weeks lateforecast Nov 28, 2017

Also in Mapleton