Install six new watermain valves and rehabilitate two watermain valves within the Drayton water distribution system to address system deficiencies and improve operational flexibility
Federal contribution
$38,500
Federal share50%
of $77.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 19, 2017
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Mapleton
- Construction start
- Jun 1, 2017(actual)
- Construction end
- Dec 15, 2017(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 1, 2017
- Construction end2 weeks lateforecast Nov 28, 2017