Drayton Sewage Pumping Station Upgrades

Mapleton, Ontario

underwayDisaster MitigationDMAF
Federal contribution
$2.1M
$2,063,032
Federal share40%

of $5.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 27, 2023
today
20232024202520262027
BuiltForecast

Approved 7 months before the announcement.

Program
Disaster Mitigation and Adaptation Fund
Ultimate recipient
Township of Mapleton
Construction start
Aug 15, 2025(actual)
Construction end
May 19, 2027(forecast)

Against the original forecast

  • Construction start6 weeks lateforecast Jul 1, 2025

Also in Mapleton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62602 in the federal list. How to read these figures.