Replacement of Mailhot stream conduit
Federal contribution
$364,909
Federal share25%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 18, 2008
20082009
Built
Approved 3 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of Lac-Etchemin
- Construction start
- Apr 1, 2008(actual)
- Construction end
- Dec 31, 2008(actual)