Back to projects

Replacement of Mailhot stream conduit

Lac-Etchemin, Quebec

completeWastewaterMRIF
Federal contribution
$364,909
Federal share25%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 18, 2008
20082009
Built

Approved 3 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Apr 1, 2008(actual)
Construction end
Dec 31, 2008(actual)

Also in Lac-Etchemin

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14159 in the federal list. How to read these figures.