Renewal of water pipes
Federal contribution
$420,582
Federal share50%
of $841.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
20172018
Built
Approved 8 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Lac-Etchemin
- Construction start
- Sep 12, 2017(actual)
- Construction end
- Oct 31, 2018(actual)
Against the original forecast
- Construction start12 months lateforecast Sep 6, 2016
- Construction end5 months earlyforecast Mar 31, 2019
Also in Lac-Etchemin
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48857 in the federal list. How to read these figures.