Water Systems Upgrades
Federal contribution
$462,230
Federal share40%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
202120222023
Built
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Municipality of Lac-Etchemin
- Construction start
- Sep 1, 2020(actual)
- Construction end
- Nov 30, 2022(actual)
Against the original forecast
- Construction start3 weeks lateforecast Aug 10, 2020
- Construction end4 weeks earlyforecast Dec 30, 2022
Also in Lac-Etchemin
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56464 in the federal list. How to read these figures.