Renovation of Municipal Arena - Phase 2
Federal contribution
$658,333
Federal share33%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 14, 2009
2010
Built
Approved 3 months before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Municipality of Lac-Etchemin
- Construction start
- Jun 1, 2009(actual)
- Construction end
- Sep 20, 2010(actual)
Against the original forecast
- Construction end11 months lateforecast Oct 30, 2009
Also in Lac-Etchemin