Renovation of Municipal Arena - Phase 2

Lac-Etchemin, Quebec

completeSportCC
Federal contribution
$658,333
Federal share33%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 14, 2009
2010
Built

Approved 3 months before the announcement.

Program
Building Canada Fund - Communities Component
Construction start
Jun 1, 2009(actual)
Construction end
Sep 20, 2010(actual)

Against the original forecast

  • Construction end11 months lateforecast Oct 30, 2009