Water Systems Upgrades
Federal contribution
$731,612
Federal share40%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
today
2021202320252027
BuiltForecast
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Municipality of Lac-Etchemin
- Construction start
- Jun 17, 2024(actual)
- Construction end
- Nov 30, 2026(forecast)
Also in Lac-Etchemin
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56465 in the federal list. How to read these figures.