Construction & Demolition Debris Disposal Site

Yarmouth, Nova Scotia

completeSolid Waste ManagementMRIF
Federal contribution
$63,712
Federal share33%

of $191.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 2, 2006
20072008
Built
Program
Municipal Rural Infrastructure Fund
Construction start
Apr 28, 2006(actual)
Construction end
Mar 31, 2008(actual)

Against the original forecast

  • Construction start5 months lateforecast Nov 24, 2005
  • Construction end22 months lateforecast May 31, 2006

Also in Yarmouth