Brown Street/Cliff Street Sewer Separation

Yarmouth, Nova Scotia

completeDrinking WaterCWWF
Federal contribution
$1.6M
$1,627,346
Federal share47%

of $3.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Yarmouth
Construction start
Oct 11, 2016(actual)
Construction end
Mar 31, 2018(actual)