Pleasant Street Reconstruction
Federal contribution
$1.3M
$1,305,653
Federal share33%
of $3.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 30, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Yarmouth
- Construction start
- Aug 11, 2010(actual)
- Construction end
- Aug 3, 2011(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2010
Also in Yarmouth
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26488 in the federal list. How to read these figures.