Schedule

Announced and approvedApr 25, 2023
202320242025
Built

Approved 4 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Yarmouth
Construction start
May 7, 2024(actual)
Construction end
Mar 31, 2025(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Jun 3, 2024
  • Construction end3 months lateforecast Dec 31, 2024