Town of Yarmouth Multi-Use Pathways

Yarmouth, Nova Scotia

completeActive TransportationGIS
Federal contribution
$944,553
Federal share40%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 16, 2021
2022202320242025
Built

Approved 3 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Yarmouth
Construction start
Oct 7, 2021(actual)
Construction end
Feb 18, 2025(actual)

Against the original forecast

  • Construction start3 months lateforecast Jul 1, 2021
  • Construction end6 weeks earlyforecast Mar 31, 2025

Also in Yarmouth

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60654 in the federal list. How to read these figures.