Town of Yarmouth Multi-Use Pathways
Federal contribution
$944,553
Federal share40%
of $2.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 16, 2021
2022202320242025
Built
Approved 3 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Yarmouth
- Construction start
- Oct 7, 2021(actual)
- Construction end
- Feb 18, 2025(actual)
Against the original forecast
- Construction start3 months lateforecast Jul 1, 2021
- Construction end6 weeks earlyforecast Mar 31, 2025
Also in Yarmouth