Back to projects

Mariners Centre Expansion

Yarmouth, Nova Scotia

underwayRecreationGICB
Federal contribution
$15.9M
$15,902,200
Federal share38%

of $41.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 21, 2022
today
2023202420252026
BuiltForecast

Approved 5 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Construction start
Oct 29, 2024(actual)
Construction end
Sep 30, 2026(forecast)

Also in Yarmouth

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64768 in the federal list. How to read these figures.