Mariners Centre Expansion
Federal contribution
$15.9M
$15,902,200
Federal share38%
of $41.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 21, 2022
today
2023202420252026
BuiltForecast
Approved 5 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Mariners Centre Management Authority
- Construction start
- Oct 29, 2024(actual)
- Construction end
- Sep 30, 2026(forecast)
Also in Yarmouth