Water and Sewer Extension and Water Supply Improvements

Fogo Island, Newfoundland and Labrador

completeDrinking WaterMRIF
Federal contribution
$510,552
Federal share33%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
20082010201220142016
Built

Approved 8.4 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Oct 29, 2007(actual)
Construction end
Mar 27, 2009(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Sep 15, 2007
  • Construction end7 months lateforecast Sep 1, 2008