Fogo Road Upgrade
Fogo Island, Newfoundland and Labrador
Federal contribution
$120,663
Federal share40%
of $301.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2025
20242025
Built
Approved 19 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Fogo Island
- Construction start
- Oct 1, 2024(actual)
- Construction end
- Nov 1, 2024(actual)
Against the original forecast
- Construction start2 months lateforecast Aug 1, 2024
Also in Fogo Island
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67324 in the federal list. How to read these figures.