Water and Sewer-Phase 2,3

Fogo Island, Newfoundland and Labrador

completeDrinking WaterCC
Federal contribution
$779,213
Federal share33%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 14, 2009
2010
Built
Program
Building Canada Fund - Communities Component
Construction start
Oct 22, 2009(actual)
Construction end
Aug 13, 2010(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Oct 1, 2009
  • Construction end5 months earlyforecast Jan 1, 2011

Also in Fogo Island

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26704 in the federal list. How to read these figures.