Water and Sewer-Phase 2,3
Fogo Island, Newfoundland and Labrador
Federal contribution
$779,213
Federal share33%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 14, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Joe Batt's Arm-Barr'd Islands and Shoal Bay
- Construction start
- Oct 22, 2009(actual)
- Construction end
- Aug 13, 2010(actual)
Against the original forecast
- Construction start3 weeks lateforecast Oct 1, 2009
- Construction end5 months earlyforecast Jan 1, 2011
Also in Fogo Island
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26704 in the federal list. How to read these figures.