Barr'd Islands Watermain

Fogo Island, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$326,461
Federal share40%

of $816.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 22, 2020
20212022
Built

Approved 3 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Fogo Island
Construction start
Sep 13, 2021(actual)
Construction end
Sep 26, 2022(actual)

Against the original forecast

  • Construction start7 months earlyforecast Apr 1, 2022