Rehabilitation of Route 333 and Area Roads
Fogo Island, Newfoundland and Labrador
Federal contribution
$1.3M
$1,250,000
Federal share50%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 7, 2024
20232024
Built
Approved 23 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Construction start
- Aug 16, 2022(actual)
- Construction end
- Nov 22, 2022(actual)
Against the original forecast
- Construction start3 months lateforecast May 16, 2022
- Construction end3 weeks lateforecast Oct 31, 2022
Also in Fogo Island
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63400 in the federal list. How to read these figures.