Water Line Extensions: Church Rd., Campbell Cres., and Miller and Paddock Avenues
Robert's Arm, Newfoundland and Labrador
Federal contribution
$48,207
Federal share33%
of $144.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
20082010201220142016
Built
Approved 8.5 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Robert's Arm
- Construction start
- Sep 17, 2007(actual)
- Construction end
- Sep 30, 2008(actual)
Against the original forecast
- Construction start2 weeks lateforecast Sep 1, 2007
- Construction end4 months lateforecast Jun 1, 2008
Also in Robert's Arm
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14941 in the federal list. How to read these figures.