Remove and Replace Old Culverts

Robert's Arm, Newfoundland and Labrador

completeHighways and RoadsMRIF
Federal contribution
$28,871
Federal share33%

of $86.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2010201220142016
Built

Approved 6.5 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Robert's Arm
Construction start
Apr 28, 2010(actual)
Construction end
Jul 31, 2010(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast May 30, 2010

Also in Robert's Arm

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22773 in the federal list. How to read these figures.