Water Line Extensions; Millers Avenue, Paddocks Avenue and Sewer Line Extensions; Main Street
Robert's Arm, Newfoundland and Labrador
Federal contribution
$111,712
Federal share33%
of $335.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2010201220142016
Built
Approved 6.7 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Robert's Arm
- Construction start
- Jun 30, 2009(actual)
- Construction end
- Jul 31, 2010(actual)
Against the original forecast
- Construction start2 months earlyforecast Sep 1, 2009
- Construction end8 months lateforecast Dec 1, 2009
Also in Robert's Arm
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 21852 in the federal list. How to read these figures.