Back to projects

Water Main Replacement - Town of Roberts Arm

Robert's Arm, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$352,572
Federal share40%

of $881.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
202020212022
Built

Approved 4 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Roberts Arm
Construction start
Jun 8, 2021(actual)
Construction end
Dec 15, 2021(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2021

Also in Robert's Arm