Water Supply Improvements
Robert's Arm, Newfoundland and Labrador
Federal contribution
$152,053
Federal share50%
of $304.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Roberts Arm
- Construction start
- Jun 1, 2018(actual)
- Construction end
- Jul 1, 2018(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 1, 2018
- Construction end6 months earlyforecast Dec 30, 2018
Also in Robert's Arm
- Water Main Replacement - Town of Roberts Arm$352.6K
- Water Line Extensions; Millers Avenue, Paddocks Avenue and Sewer Line Extensions; Main Street$111.7K
- Sewage Treatment Plant Enclosure$68.5K
- Water Line Extensions: Church Rd., Campbell Cres., and Miller and Paddock Avenues$48.2K
- Remove and Replace Old Culverts$28.9K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46958 in the federal list. How to read these figures.