Water Supply Improvements

Robert's Arm, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$152,053
Federal share50%

of $304.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Roberts Arm
Construction start
Jun 1, 2018(actual)
Construction end
Jul 1, 2018(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 1, 2018
  • Construction end6 months earlyforecast Dec 30, 2018

Also in Robert's Arm

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46958 in the federal list. How to read these figures.