Improvements to the Water Supply System

Dutton/Dunwich, Ontario

completeDrinking WaterMRIF
Federal contribution
$1.3M
$1,321,891
Federal share33%

of $4.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 10, 2007
20072008200920102011
Built

Approved 3 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Feb 1, 2007(actual)
Construction end
Dec 30, 2010(actual)

Against the original forecast

  • Construction end3 months earlyforecast Mar 31, 2011

Also in Dutton/Dunwich

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15150 in the federal list. How to read these figures.