County of Elgin's LTCH Rooftop HVAC Replacement
Federal contribution
$166,231
Federal share80%
of $207.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- County of Elgin
- Construction start
- Dec 14, 2021(actual)
- Construction end
- Jan 14, 2022(actual)
Against the original forecast
- Construction end2 months earlyforecast Mar 31, 2022