Improvements to Sewer System

Dutton/Dunwich, Ontario

completeWastewaterISF
Federal contribution
$341,667
Federal share33%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 1, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start8 months lateforecast Dec 1, 2009
  • Construction end4 weeks lateforecast Sep 30, 2011

Also in Dutton/Dunwich

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30391 in the federal list. How to read these figures.