Replacement of Celtic Culvert
Federal contribution
$164,000
Federal share33%
of $492.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Municipality of Dutton/Dunwich
- Construction start
- Aug 11, 2009(actual)
- Construction end
- Dec 12, 2009(actual)
Also in Dutton/Dunwich
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24588 in the federal list. How to read these figures.