Ash Line Culvert Replacement and Resurfacing
Federal contribution
$669,377
Federal share60%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 24, 2020
20212022
Built
Approved 5 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Municipality of Dutton Dunwich
- Construction start
- Nov 1, 2021(actual)
- Construction end
- Jul 29, 2022(actual)
Against the original forecast
- Construction end4 weeks lateforecast Jun 30, 2022
Also in Dutton/Dunwich
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54570 in the federal list. How to read these figures.