Ash Line Culvert Replacement and Resurfacing

Dutton/Dunwich, Ontario

completeHighways and RoadsRNIS
Federal contribution
$669,377
Federal share60%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 24, 2020
20212022
Built

Approved 5 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Nov 1, 2021(actual)
Construction end
Jul 29, 2022(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Jun 30, 2022

Also in Dutton/Dunwich

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54570 in the federal list. How to read these figures.