43rd Avenue Storm Sewer Trunk Extension
Federal contribution
$1.2M
$1,165,349
Federal share33%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 13, 2007
2007200820092010
Built
Approved 7 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Cold Lake
- Construction start
- Jan 23, 2007(actual)
- Construction end
- Mar 12, 2010(actual)
Against the original forecast
- Construction start16 months lateforecast Sep 20, 2005
Also in Cold Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15501 in the federal list. How to read these figures.