Replacement of two aging core fleet vehicles to modernize transit fleet and increase accessibility

Cold Lake, Alberta

completePublic TransitPTIF
Federal contribution
$174,000
Federal share17%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 3, 2016
20172018
Built

Approved 4 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Cold Lake
Construction start
Sep 1, 2017(actual)
Construction end
Aug 31, 2018(actual)

Against the original forecast

  • Construction start8 months lateforecast Jan 1, 2017
  • Construction end2 months earlyforecast Nov 1, 2018

Also in Cold Lake

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47832 in the federal list. How to read these figures.