Replacement of two aging core fleet vehicles to modernize transit fleet and increase accessibility
Federal contribution
$174,000
Federal share17%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 3, 2016
20172018
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Cold Lake
- Construction start
- Sep 1, 2017(actual)
- Construction end
- Aug 31, 2018(actual)
Against the original forecast
- Construction start8 months lateforecast Jan 1, 2017
- Construction end2 months earlyforecast Nov 1, 2018