English Bay Road
Federal contribution
$1.8M
$1,775,480
Federal share33%
of $5.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 8, 2007
20082009201020112012
Built
Approved 2 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Cold Lake
- Construction start
- Feb 19, 2008(actual)
- Construction end
- Nov 4, 2011(actual)
Also in Cold Lake
- 43rd Avenue Storm Sewer Trunk Extension$1.2M
- Cold Lake - Community Trails Network Enhancements$706.9K
- Cold Lake - Transit Fleet Enhancement$260.0K
- Replacement of two aging core fleet vehicles to modernize transit fleet and increase accessibility$174.0K
- Cold Lake - Building #5/#7/#10 HVAC Retrofit Upgrades$17.9K