Cold Lake - Building #5/#7/#10 HVAC Retrofit Upgrades

Cold Lake, Alberta

completeVentilationCVRIS
Federal contribution
$17,881
Federal share75%

of $23.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 28, 2024
2024
Built

Approved 11 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Cold Lake
Construction start
Aug 8, 2023(actual)
Construction end
Aug 9, 2023(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 1, 2023
  • Construction end3 weeks earlyforecast Aug 31, 2023

Also in Cold Lake

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67670 in the federal list. How to read these figures.