Cold Lake - Transit Fleet Enhancement
Federal contribution
$260,000
Federal share40%
of $650.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 4, 2021
Built
Approved 7 weeks before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Cold Lake
- Construction start
- Mar 19, 2021(actual)
- Construction end
- Jul 31, 2021(actual)
Against the original forecast
- Construction start2 months earlyforecast May 25, 2021
- Construction end2 weeks lateforecast Jul 15, 2021
Also in Cold Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58788 in the federal list. How to read these figures.