Back to projects

Township of Woolwich Asset Management

Elmira, Ontario

completeCapacity BuildingMRIF
Federal contribution
$6,068
Federal share33%

of $18.2K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedJun 18, 2007
200720082009
Built

Approved 6 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of Woolwich
Construction start
Jun 18, 2007(actual)
Construction end
Jan 21, 2009(actual)

Against the original forecast

  • Construction end2 months earlyforecast Mar 31, 2009

Also in Elmira