Snyder Avenue Reconstruction

Elmira, Ontario

completeWastewaterISF
Federal contribution
$866,667
Federal share33%

of $2.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Woolwich
Construction start
May 14, 2010(actual)
Construction end
Oct 29, 2010(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Apr 15, 2010
  • Construction end5 weeks earlyforecast Nov 30, 2010