Back to projects

Samuel Street and Area Reconstruction

Elmira, Ontario

completeWastewaterISF
Federal contribution
$866,667
Federal share33%

of $2.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Woolwich
Construction start
May 3, 2010(actual)
Construction end
Nov 19, 2010(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Apr 15, 2010
  • Construction end4 weeks earlyforecast Dec 15, 2010

Also in Elmira

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31627 in the federal list. How to read these figures.