Reconstruction of Riverside Drive West

Elmira, Ontario

completeDrinking WaterMRIF
Federal contribution
$270,000
Federal share33%

of $810.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedFeb 19, 2008
ApprovedMar 26, 2008
2009
Built

Approved 5 weeks after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of Woolwich
Construction start
Mar 26, 2008(actual)
Construction end
Feb 28, 2009(actual)

Against the original forecast

  • Construction end5 months lateforecast Sep 30, 2008