Replacement and Upgrading of the Water and Wastewater Services
Federal contribution
$743,601
Federal share33%
of $2.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Township of Woolwich
- Construction start
- May 25, 2009(actual)
- Construction end
- Oct 29, 2010(actual)
Also in Elmira
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24604 in the federal list. How to read these figures.