Replacement and Upgrading of the Water and Wastewater Services

Elmira, Ontario

completeDrinking WaterCC
Federal contribution
$743,601
Federal share33%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2010
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Township of Woolwich
Construction start
May 25, 2009(actual)
Construction end
Oct 29, 2010(actual)