McDougall Asset Management
Federal contribution
$4,156
Federal share33%
of $12.5K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedDec 6, 2006
ApprovedJun 27, 2007
20072008
Built
Approved 7 months after the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of McDougall
- Construction start
- Jun 27, 2007(actual)
- Construction end
- Mar 27, 2008(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 1, 2007
- Construction end3 months lateforecast Dec 31, 2007
Also in Nobel
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17857 in the federal list. How to read these figures.