Water and Sewer Upgrades
Trinity Bay North, Newfoundland and Labrador
Federal contribution
$758,549
Federal share33%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2010201220142016
Built
Approved 6.7 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Bide Arm
- Construction start
- Aug 10, 2010(actual)
- Construction end
- Jul 27, 2011(actual)
Against the original forecast
- Construction start10 months lateforecast Oct 1, 2009
- Construction end11 months lateforecast Sep 1, 2010
Also in Trinity Bay North