Catalina Sea Wall

Trinity Bay North, Newfoundland and Labrador

underwayDisaster MitigationGIS
Federal contribution
$276,222
Federal share40%

of $690.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 20, 2024
202420252026
BuiltForecast

Approved 5 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Trinity Bay North
Construction start
Oct 24, 2024(actual)
Construction end
Dec 15, 2025(forecast)

Against the original forecast

  • Construction start5 months earlyforecast Apr 8, 2025

Also in Trinity Bay North