Catalina Sea Wall
Trinity Bay North, Newfoundland and Labrador
Federal contribution
$276,222
Federal share40%
of $690.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 20, 2024
202420252026
BuiltForecast
Approved 5 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Trinity Bay North
- Construction start
- Oct 24, 2024(actual)
- Construction end
- Dec 15, 2025(forecast)
Against the original forecast
- Construction start5 months earlyforecast Apr 8, 2025
Also in Trinity Bay North