Catalina Bar Bridge Replacement
Trinity Bay North, Newfoundland and Labrador
Federal contribution
$166,267
Federal share33%
of $498.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2016
20172018
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Trinity Bay North
- Construction start
- Aug 31, 2017(actual)
- Construction end
- Oct 31, 2018(actual)
Against the original forecast
- Construction start5 months lateforecast Apr 1, 2017
- Construction end3 months lateforecast Jul 30, 2018
Also in Trinity Bay North