Catalina Bar Bridge Replacement

Trinity Bay North, Newfoundland and Labrador

completeHighways and RoadsSCF
Federal contribution
$166,267
Federal share33%

of $498.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2016
20172018
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Trinity Bay North
Construction start
Aug 31, 2017(actual)
Construction end
Oct 31, 2018(actual)

Against the original forecast

  • Construction start5 months lateforecast Apr 1, 2017
  • Construction end3 months lateforecast Jul 30, 2018